Here is a list of submittal
codes used by RMS
. The government user will then, after review of the submittal, use one of the other codes. Codes that require a resubmittal of the submittal are indicated by the status of "Resubmit".
| Code | Description | Status |
|---|---|---|
| A |
Approved as submitted |
Completed |
| B | Approved, except as noted on drawings |
Completed |
| C | Approved, resubmission required |
Resubmit |
| D | Returned by correspondence |
Completed |
| E | Disapproved |
Resubmit |
| F | Receipt acknowledged |
Completed |
| G | Other |
Resubmit |
| K | Government concurs with Interim Design |
Completed |
| R | Acceptable for Release for Construction |
Completed |
| X | Receipt acknowledged, does not comply |
Resubmit |